Bullen Warehouse Expansion with Roof Deck

8 Mar

Warehouse Facility Construction Phladelphia PA
Structural steel nearing completion. Metal pan deck on mezzanine in preparation for concrete pour. Roof deck completed and metal frames installed for skylights.

Facade Replacement Philadelphia PA
Selective demolition underway on existing building façade. Crew is removing former mansard roof which will be replaced with a more contemporary stucco façade.

Construction Warehouse Expansion Folcroft, PA
View from the rear of the building. Sloped roof steel to promote drainage, backfill of foundation and storm water inlet piping is underway.

Construction warehouse expansion philadelphia, pa
View inside the warehouse. New stair tower and stairs to storage mezzanine are complete. Rough grading is underway in preparation for layout and installation of underground utilities.

Warehouse Expansion Philadelphia
View of front of building. Crews are staging masonry materials in readiness for constructing exterior walls while steel erectors install safety cabling on the mezzanine.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: